How to Build a Shooting Schedule on the Stripboard

Choose what strips show, set the number of shoot days, read strips and End of Day markers, let the optimizer suggest a shooting order, then lock strips, add a company move, use the Boneyard, try scenarios and lock whole days to the plan.

Loads from YouTube on play

Recorded against The Long Way Home. To build the same project as you watch, download the project files (5 MB).

In this episode

  • 0:00 Introduction
  • 0:16 Strips and shoot days
  • 2:48 The Inspector
  • 3:50 Optimizing the schedule
  • 5:20 Adjusting by hand
  • 6:39 Scenarios
  • 8:06 Summary and next steps

With the breakdown done, we can start scheduling The Long Way Home. In this episode we set the number of shoot days, read the stripboard, ask the optimizer for a shooting order, and then adjust it by hand. For the wider picture, see the film scheduling software page.


Step 1: Read the Strips and Choose What They Show

  1. Click the Schedule tab and select Stripboards in the sidebar.

Every scene is a strip, and the strips are in script order for now. The columns show the scene number, interior or exterior, day or night, the location, the set, the cast numbers, the story day, the length in pages and the screen time. The color comes from the location, so scenes at the same place share a color, and you can see at a glance how often the story moves around.

What a strip shows is up to you.

  1. Click the gear in the top bar to open Settings, and select Stripboard under Global.

Style changes the look of the strips, Color mode decides where their color comes from, and the strip columns choose what each strip shows.

  1. If you’re used to the industry’s paper stripboard, switch Color mode to Industry standard and press Escape to see it. The strips follow the standard colors: white for interior day, yellow for exterior day, blue for interior night, green for exterior night and orange for dawn and dusk.
  2. For this series we stay with By location, which gives each place its own color and each set there a shade of it, so open Settings again and switch Color mode back to By location. Leave Story day on under the strip columns, because the costume department will ask about it.
  3. Press Escape to go back to the board.

These are global settings, so every project’s board looks the same.

Compact view in the toolbar puts every strip on one line, and Expanded view brings the synopsis back. We stay on Expanded view, because the synopsis tells you what happens in a scene, and that often decides where it goes in the schedule.

  1. Click scene 3’s synopsis on its strip. It becomes an edit box. Type a shorter line and press Return. The change is kept on the strip, and the script stays as it is.

Step 2: Set the Number of Shoot Days

A schedule needs to know how many days it has.

  1. Click the 0 shoot days button in the toolbar (tooltip “Shoot days are set on the Production schedule”). FilmBase takes you to the Production schedule, where the count lives.
  2. Click the shoot days box in its toolbar, type 8 and press Return.
  3. Select Stripboards in the sidebar to come back.

The board now has eight End of Day markers, and the strips are divided between them. Each marker closes a shoot day. It reads END OF DAY 1, END OF DAY 2 and so on, with the date and the total pages of the scenes above it, so a day with too many pages stands out. It also has boxes for the Call and Wrap times, and once you give the strips an estimated time, the marker adds those up as well.


Step 3: Open the Inspector

  1. Click the strip for scene 14. The Inspector opens on the right, on its Details tab.

Details shows the scene’s synopsis, story day, page count and cast, and the real-world place it shoots, under Real world set. It reads Not assigned for now; we set it when we add locations in Episode 8. Shooting mode is for scenes shot one way and set another, such as a night scene shot in daylight with the windows covered.

Since this is a short film, we shoot all six night scenes during the day, with blackout on the windows for the interiors and the exteriors darkened in the grade.

  1. Click the strip for scene 18 (EXT. LAKE WENDAWAY - GUS’S CABIN - NIGHT), open Shooting mode in the Inspector and choose Day for night. The strip’s day/night column now reads DfN, and the optimizer treats the scene as a day scene.
  2. Set scenes 1, 10, 11, 19 and 20 to Day for night the same way.

Step 4: Choose the Optimizer Settings

  1. Click Optimize in the toolbar. The Inspector switches to its Optimize tab, with the Optimize schedule button and “25 scenes · 8 shoot days” under it.

The optimizer looks at every scene, location, cast member and constraint and suggests an order that keeps company moves and actor days down.

The presets under Priority set the sliders for you:

  • Locations keeps each place together so the crew moves as little as possible.
  • Actors keeps each performer’s days close together.
  • Balanced sits between the two.
  1. The Long Way Home goes back to the same diner, garage and motel twice, so click Locations.

You can drag any slider afterwards, such as Actor focus, Follow script order or Keep locations together, and the preset changes to Custom.

  1. Scroll down to Scheduling rules and leave Keep day/night separate on.

That rule stops a day from mixing day and night scenes. A scene shot day for night counts as a day scene, so with our night scenes set that way the rule can stay on. Leave Use all shoot days on too.

Further down:

  • Hard limits cap the day with Max pages/day and Max locations/day.
  • Solve time sets how long the optimizer works: Quick, Smart or Thorough.
  • Constraints are the rules the optimizer never breaks: Cast availability, Location availability and Minimum turnaround, which is the rest hours between one day’s wrap and the next day’s call.

Step 5: Run the Optimizer

  1. Scroll back up and click Optimize schedule. A progress bar runs while it works.
  2. The result card says Optimization complete, with Undo and Done.

Scenes at the same place now sit together, so the crew isn’t sent back and forth. If you don’t like the result, Undo puts your previous board back exactly as it was.

  1. Click Done to keep it.

Step 6: Move and Lock a Strip

The optimizer gives you a starting point, and you know things it doesn’t. Our director wants the garage scenes shot on the first day while the house is ours.

  1. Drag the strip for scene 1 into Day 1, beside scenes 2 and 3.
  2. Right-click it and choose Lock to day. A lock icon appears on the strip, and the next optimizer run leaves it where it is.

Step 7: Add a Company Move

When the unit changes location in the middle of a day, mark it on the board.

  1. Right-click the last strip at Dot’s House on Day 1 and choose Add company move.
  2. In the Add company move dialog, type Highway 9 into Destination.
  3. Set Estimated time (minutes) to 45 and click Add.

A banner reading COMPANY MOVE TO HIGHWAY 9 appears below the strip. It prints on the schedule, so everyone knows the move is coming. If you run the optimizer again later, the banner moves with the scene that comes after it, so it stays in front of the new location.


Step 8: Use the Boneyard

If a scene might be cut, don’t delete it. Move it to the boneyard, and the strip leaves the schedule and the call sheets but stays in the project.

  1. Right-click the strip for scene 5 and choose Move to boneyard. The strip disappears from the board.
  2. Click Boneyard in the toolbar. The Boneyard window lists scene 5.
  3. Right-click it and choose Restore to stripboard, then close the window.

Step 9: Try a Scenario

Each tab above the board is a scenario, which is another arrangement of the same scenes.

  1. Click the + at the top right of the tabs and choose Create new scenario. A second tab opens beside Master.
  2. Right-click the new tab to see Set as master, Rename, Duplicate tab and Delete scenario. Choose Rename, type Locations first and press Return. It keeps the optimizer’s order to compare against.

Use scenarios to try a different order without losing the one you have. The tab with the star is the master, and that’s the one the call sheets, the Day out of Days and the reports use.


Step 10: Arrange the Board to the Plan and Lock the Days

Our first assistant director has written a plan for the eight days. In the video it’s on a pause card, and it’s also in the follow-along guide in the project files on the series page.

  1. Click the Master tab.
  2. Pause and drag your strips into the same days, in the same order, the way we moved scene 1:
DayScenes, in order
114, 15, 16
22, 3, 1, (company move), 7
36, 10, 12, 8
44, 9, 11
517, 18, 19, 20
613, 5
721, 22
825, 23, 24

The farmers’ market, scenes 14 to 16, goes first for now. It has to be shot on a real market Saturday, and in the next episode we put that day on the right date on the Production schedule, so keep it as Day 1. The Dot’s House day, with the company move, is Day 2 until then.

When the days match the plan, lock them, so a later optimizer run can’t undo your work.

  1. Click the strip for scene 14, hold Shift and click the strip for scene 16 to select the whole day.
  2. Right-click and choose Lock to day. Lock icons appear on all three strips.
  3. Do the same for each of the other seven days.

We have eight shoot days in a sensible order, with a company move on the Dot’s House day and a second scenario to try ideas in. In the next episode, The Production Schedule, we put those days on real dates, with prep, a rehearsal, a day off and a wrap day.

Common questions

What is a stripboard in film scheduling?

A stripboard shows every scene as a strip, with its scene number, interior or exterior, day or night, location, cast and page count. You arrange the strips into shoot days, and End of Day markers divide the board, so each day's pages and screen time are easy to read.

How does a schedule optimizer decide the shooting order?

It looks at every scene, location, cast member and constraint and suggests an order that keeps company moves and actor days down. In FilmBase you choose a priority (Locations, Balanced or Actors), set rules such as keeping day and night scenes apart, and the optimizer never breaks constraints like an actor's unavailable dates or the rest hours between days.

What is a company move?

A company move is when the whole unit packs up and relocates to another location in the middle of a shoot day. In FilmBase you right-click the last strip before the move, choose Add company move, and enter the destination and an estimated time, and a banner prints on the schedule.

How do I take a scene off the schedule without deleting it?

Right-click its strip and choose Move to boneyard. The scene leaves the schedule and the call sheets but stays in the project. The Boneyard button lists those scenes, and Restore to stripboard brings one back.